- Dubai authority path
- Complete the approved erection and record structural, electrical, access and safety-device commissioning results.
- Abu Dhabi authority path
- The crane must remain within the plot boundary and present zero collision risk in any configuration, including out of service.
- Required controlled evidence
- Erection records, pin / bolt / torque and tie controls, earthing and electrical checks, brake, limit, SLI/RCI, anti-two-block, anemometer and anti-collision test results.
- Hold / release criterion
- No operation before defects are closed and the technical file is complete.
- Responsible lead
- Erection subcontractor
- Independent verifier
- Engineer / HSE