Learning Objectives

  • Sequence enabling works safely before main construction.
  • Identify and isolate live buried and overhead services.
  • Manage demolition, clearance and hazardous material discovery.
  • Erect compliant hoarding, access and site security.
  • Handover a de-risked site to the main works contractor.

Awareness Video

Pro

Preview

8-minute video

Unlock this awareness video

The first 3 modules are free. Upgrade to Pro to watch every module, save progress, and issue certificates.

Upgrade to Pro

Module Content

1. Scope of Enabling Works

Everything that must be complete before main construction can start safely: site clearance, demolition, tree removal, service diversions (power, water, gas, telecoms, drainage), ground investigation, temporary hoarding, access roads, welfare setup and utility connections.

2. Buried & Overhead Service Detection

Utility record drawings + CAT & Genny sweep + trial holes before any mechanical excavation. Overhead lines: minimum clearances to DEWA/ADDC/SEWA specification; goalposts and bunting. Never assume a service is dead — prove-dead with lockout and instrumentation.

3. Demolition Safety

Pre-demolition survey (structural, asbestos, hazardous materials). Method statement approved by structural engineer. Exclusion zones, dust suppression, edge protection on remaining structures. Progressive demolition — never remove load paths without temporary supports.

4. Hazardous Material Discovery

Stop-work triggers: asbestos-suspected material, contaminated soil, unexploded ordnance, abandoned services, buried tanks. Cordon, do not disturb, notify environmental consultant and authorities. Restart only with a documented safe-disposal method statement.

5. Hoarding, Access & Security

Municipality-approved hoarding height and setback; corner sightlines; gate banksman; separate pedestrian entry. Site security 24/7 during enabling to prevent unauthorised access to open excavations, live services or demolition debris.

6. Handover to Main Works

Enabling contractor issues a formal handover pack: as-built service isolations, remaining hazards register, ground conditions, dilapidation survey of adjacent properties, permits closed. Main contractor accepts in writing before mobilising the primary workforce.

Knowledge Assessment

1. Enabling works are:

2. Before mechanical excavation you must:

3. Overhead power lines require:

4. Demolition sequencing must:

5. Suspected asbestos during clearance means:

6. Site hoarding is:

7. 24/7 security during enabling prevents:

8. 'Prove dead' on isolated services means:

9. Dilapidation survey covers:

10. Handover to the main contractor must be:

Certificate

Pass the quiz (8 / 10) to unlock your certificate.

Acknowledgement

By signing below, you confirm you have watched the awareness video, understood the material, and will apply these controls on site.

Complete the video and pass the quiz (8 / 10) to unlock signing.

Next step

Turn this into evidence you can hand over

Bilingual awareness modules your supervisors can run in a toolbox talk, with an internal completion record afterwards.

  • Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
  • Usable the same dayTemplates and registers are pre-filled with your company details.
  • Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.