Ground Works

Excavation & Trenching Safety

UAE excavation hazards, NOCs, GPR scanning, shoring and battering, confined space considerations, and the competent person inspection regime.

v2.0Updated 15 Feb 2026ADOSH-SF v4.1 (February 2026)
7 min
Video
10
Quiz questions
8 / 10
Pass threshold
0%
Your progress

Learning Objectives

  • Identify the UAE authorities requiring NOCs before excavation.
  • Apply GPR (Ground Penetrating Radar) scanning before breaking ground.
  • Select shoring, battering or benching based on soil and depth.
  • Recognise when a trench becomes a confined space.
  • Conduct the daily competent person inspection.

Awareness Video

Pro

Preview

7-minute video

Unlock this awareness video

The first 3 modules are free. Upgrade to Pro to watch every module, save progress, and issue certificates.

Upgrade to Pro

Module Content

1. NOCs & Utilities

Before any excavation on a UAE site, NOCs are required from DEWA/ADDC/SEWA, Etisalat/du, Empower, ADNOC (fuel lines) and the municipality. Utility drawings are cross-checked with GPR scan. Trial pits by hand-digging expose services.

2. GPR Scanning

GPR is mandatory before breaking ground on brownfield sites. Positive scan = utility present = do not dig until utility is confirmed and de-energised or diverted. Negative scan does not replace hand-digging trial pits.

3. Shoring & Battering

Trenches deeper than 1.2 m require support: shoring (hydraulic props, trench boxes), battering to the angle of repose, or benching. Choice depends on soil type, water table, adjacent loads and depth.

4. Confined Space

Any excavation deeper than 1.2 m with restricted access or potential for atmosphere accumulation (e.g. contaminated ground, adjacent gas main) is a confined space. Confined space PTW, gas monitor, rescue plan and standby person are mandatory.

5. Access & Egress

Ladder within 7.5 m of every worker, secured, extending 1 m above the excavation edge. No jumping in or climbing out on shoring.

6. Competent Person Inspection

Daily inspection by a competent person before shift start, after rain, after any collapse or loading change. Recorded in the excavation register. Excavation red-tagged if any deficiency is found.

Knowledge Assessment

1. NOCs before excavation on a UAE site are required from:

2. GPR scanning is mandatory:

3. Trenches deeper than what depth require support?

4. A trial pit is best excavated by:

5. A ladder in an excavation must be within what distance of every worker?

6. A trench > 1.2 m deep with restricted access is treated as:

7. Excavation inspections must be recorded:

8. If a positive GPR scan is returned:

9. A negative GPR scan means:

10. Battering an excavation means:

Certificate

Pass the quiz (8 / 10) to unlock your certificate.

Acknowledgement

By signing below, you confirm you have watched the awareness video, understood the material, and will apply these controls on site.

Complete the video and pass the quiz (8 / 10) to unlock signing.

Next step

Turn this into evidence you can hand over

Bilingual awareness modules your supervisors can run in a toolbox talk, with an internal completion record afterwards.

  • Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
  • Usable the same dayTemplates and registers are pre-filled with your company details.
  • Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.