UAE construction safety reference

What does MSRA stand for? Method Statement Risk Assessment, explained for UAE sites

Updated 9 September 2026

Short answer

MSRA stands for Method Statement Risk Assessment — one controlled document that sets out, step by step, how a task will be carried out safely, and scores the hazards and controls for each of those steps. In the UAE it is the document a client, consultant or authority inspector asks for before high-risk work starts, and it must be signed by the preparer, a competent reviewer and the site's HSE manager before a permit to work is issued.

Key points

  • MSRA = Method Statement + Risk Assessment. RAMS (Risk Assessment and Method Statement) is the same document with the two words reversed — the terms are used interchangeably on UAE sites.
  • The method statement describes the sequence of work; the risk assessment scores each hazard, usually on a 5×5 likelihood × severity matrix, before and after controls.
  • An MSRA must be task and site specific. A generic template with another project's name on it is the most common reason an MSRA is rejected at review.
  • MSRAs are referenced directly by permits to work — the permit authorises the activity, the MSRA defines how it is done.
  • UAE reviewers (MOHRE, ADOSH-SF, Dubai Municipality, Civil Defence, Trakhees) expect the MSRA to name the competent persons, the plant and equipment, the emergency arrangements and the third-party certification relied on.
  • There is no single national MSRA form. Each authority and each client HSE plan sets its own required content, so the document must be written to the strictest requirement that applies to your site.

MSRA definition in full

A Method Statement Risk Assessment is a controlled, task-specific safety document combining two things that used to be issued separately: a written method statement describing how a job will be done, and a risk assessment identifying what could go wrong at each stage and how it is controlled. Combining them means a reviewer can read a work step and the controls for that step side by side, which is why UAE main contractors and consultants now insist on the combined format for any high-risk activity.

  • Controlled — it carries a document number, revision, date and signatures, and supersedes earlier revisions.
  • Task specific — written for one activity on one site, not a library document reused across projects.
  • Evidence backed — competency cards, third-party certificates, drawings, lifting plans and SDS sheets are attached.
  • Live — revised whenever the method, plant, personnel or site conditions change.

What the two halves cover

The method statement is the 'how': scope, sequence of operations, resources, plant, temporary works, permits required, supervision and emergency arrangements. The risk assessment is the 'what could go wrong': each hazard, who could be harmed, the initial risk score, the controls applied and the residual score after those controls.

  • Method statement — scope, step-by-step sequence, plant and equipment, competency, permits, emergency and rescue plan.
  • Risk assessment — hazard, persons at risk, initial score, control measures, residual score, responsible person.
  • Appendices — drawings, lifting plans, SDS sheets, third-party certificates, competency cards.

How the risk assessment half is scored

Most UAE projects use a 5×5 matrix: likelihood 1–5 multiplied by severity 1–5, giving a score of 1–25. The initial score is recorded before controls, the residual score after them. Reviewers check that the residual score is justified by the controls actually described in the method — dropping a score from 20 to 4 with 'toolbox talk' as the only control is a standard rejection.

  • 1–5 low — proceed with normal supervision and the stated controls.
  • 6–12 medium — controls verified before start, supervision named in the document.
  • 15–25 high — work does not proceed until the method is redesigned or additional controls reduce the score; usually requires client or consultant approval.
  • Apply the hierarchy of control in order — eliminate, substitute, engineering, administrative, PPE — rather than defaulting to PPE.

UAE regulations and standards behind the MSRA

No single UAE law uses the word 'MSRA', but several instruments require the risk assessment and safe system of work that the MSRA documents. Which ones apply depends on the emirate and the jurisdiction your site sits in.

  • Federal Decree-Law No. 33 of 2021 on the Regulation of Employment Relations and its implementing decisions — the employer's duty to assess and control occupational risk; enforced by MOHRE.
  • Ministerial Decision No. 32 of 2022 on occupational health and safety and labour accommodation — risk prevention, competency and supervision requirements applied on labour-intensive sites.
  • ADOSH-SF (formerly OSHAD SF) — Abu Dhabi's system framework; the risk-management and permit elements set the expected content of a method statement and risk assessment for entities under Abu Dhabi jurisdiction.
  • Dubai Municipality Code of Construction Safety Practice — risk assessment, method statements and permit-to-work requirements for Dubai construction sites.
  • Trakhees / Ports, Customs and Free Zone Corporation HSE requirements — applies in Trakhees-regulated free zones and requires submitted and approved method statements for high-risk activity.
  • UAE Civil Defence requirements and the UAE Fire and Life Safety Code of Practice — hot work, fire watch and impairment controls referenced inside the MSRA and the associated permit.
  • ISO 45001:2018 clause 6.1.2 (hazard identification and assessment of risk) and clause 8.1 (operational planning and control) — used by most clients as the audit reference for MSRA quality.
  • Client and consultant project HSE plans — routinely stricter than the authority baseline; check the submission and approval timescale, often 7 to 14 days before mobilisation.

Roles and responsibilities

An MSRA fails audit as often for a missing role as for a missing control. Every UAE project should be able to name the person in each of these roles for each MSRA, and the document should show their signature and date.

  • Preparer — usually the subcontractor's engineer or HSE officer who owns the method. Must have practical knowledge of the task, not just the template.
  • Risk assessor — a competent person (typically NEBOSH/IOSH qualified) who scores hazards and validates the controls against the hierarchy of control.
  • Reviewer — the main contractor's HSE manager, who checks that scores match the described method and that certificates and drawings are attached.
  • Approver — the project manager, and on most projects the client's or consultant's HSE representative, who accepts residual risk on behalf of the project.
  • Permit issuer / authorised person — issues the permit to work referencing the approved MSRA and validates that site conditions match it.
  • Supervisor — briefs the workforce on the MSRA in a language they understand, records the briefing register and stops work if the method changes.
  • Workforce — sign the briefing register, work to the stated sequence and raise a stop-work when conditions differ from the document.
  • Document controller — holds the revision register so only the current revision is in circulation on site.

MSRA vs RAMS vs JSA vs permit to work

MSRA and RAMS describe the same controlled document and are used interchangeably across the Gulf. A JSA (Job Safety Analysis) or JHA is a shorter, task-level breakdown often produced at the workface on the day; it supports the MSRA rather than replacing it. A permit to work is the authorisation to begin, issued against an approved MSRA and valid only for the stated window, location and crew.

When an MSRA is required in the UAE

Any high-risk activity: work at height, excavation, confined space, hot work, lifting operations, demolition, energised electrical work, work over water, and any activity a client's HSE plan designates as critical. Most main contractors also require an MSRA for a new subcontractor's first mobilisation regardless of the trade, and a fresh revision whenever plant, crew or sequence changes.

Why MSRAs get rejected

Reviewers reject an MSRA when it is generic, when the risk scores do not match the described method, when named competent persons have no attached certification, when the emergency and rescue plan is missing for height or confined space work, when the briefing is not recorded in the workforce's language, or when the document is unsigned or undated. Rebuilding the MSRA as a structured record — rather than a Word file passed around by email — removes most of these.

How to write an MSRA, step by step

Work through the same sequence every time so nothing is lost between revisions.

  • 1. Define the scope, location and duration of the single activity being covered.
  • 2. Break the activity into work steps in the order they will actually happen on site.
  • 3. List the hazards per step and who is exposed, including other trades and the public.
  • 4. Score each hazard on the 5×5 matrix before controls.
  • 5. Apply controls using the hierarchy of control, then record the residual score.
  • 6. Name the competent persons, plant, certificates and permits each step depends on.
  • 7. Write the emergency and rescue arrangements, including rescue from height or confined space.
  • 8. Attach drawings, lifting plans, SDS sheets and competency evidence.
  • 9. Route for review, approval and signature, then brief the crew and record the register.
  • 10. Revise and re-approve whenever the method, plant, personnel or conditions change.

Checklists and templates to use with your MSRA

Use the MSRA content checklist to self-check a document before submitting it, then use the activity checklist for the work itself so the controls written in the MSRA are verified in the field. All are free and printable, and the templates pack covers the eight highest-risk UAE construction activities.

  • MSRA content checklist — checks the document itself before submission.
  • Working at height, excavation and shoring, lifting operations, confined space entry and hot work checklists — verify the controls on site.
  • Permit to work audit checklist — confirms each permit references an approved, current MSRA.
  • MSRA / RAMS templates pack — editable starting points aligned to ADOSH-SF, Dubai Municipality and MOHRE expectations.

How to produce one quickly

Start from a task-specific template, adapt every step to the actual site, score the hazards with your own 5×5 matrix, attach the certificates and drawings, then route it for review and signature. Site Safety UAE provides eight controlled MSRA templates and an MSRA builder that scores the risks, captures sign-offs and produces a signed PDF pack for submission.

How to write an MSRA (Method Statement Risk Assessment)

The ten-step process UAE reviewers expect: define the scope, break the task into work steps, score each hazard on a 5×5 matrix before and after controls, name competent persons, add emergency arrangements, attach evidence, and route for review, approval and crew briefing.

  1. Define the scope

    Define the scope, location and duration of the single activity the MSRA covers.

  2. Break the activity into work steps

    List the work steps in the order they will actually happen on site.

  3. Identify hazards per step

    List the hazards for each step and who is exposed, including other trades and the public.

  4. Score the initial risk

    Score each hazard on the 5×5 likelihood × severity matrix before controls are applied.

  5. Apply controls and rescore

    Apply controls following the hierarchy of control, then record the residual risk score.

  6. Name competent persons and resources

    Name the competent persons, plant, certificates and permits each step depends on.

  7. Write emergency arrangements

    Write the emergency and rescue arrangements, including rescue from height or confined space.

  8. Attach the evidence

    Attach drawings, lifting plans, SDS sheets and competency evidence.

  9. Review, approve and brief

    Route the MSRA for review, approval and signature, then brief the crew and record the briefing register.

  10. Revise when anything changes

    Revise and re-approve the MSRA whenever the method, plant, personnel or site conditions change.

Put it into practice

Related checklists and tools

MSRA questions, answered

What is the full form of MSRA in safety?

Method Statement Risk Assessment. Some organisations write it as Method Statement and Risk Assessment or Method Statement & Risk Assessment; all refer to the same combined controlled document.

Is MSRA the same as RAMS?

Yes. RAMS stands for Risk Assessment and Method Statement — the same two components in the opposite order. UAE and Gulf contractors tend to say MSRA; UK-influenced clients tend to say RAMS.

Who prepares and who signs an MSRA?

It is prepared by the contractor's engineer or HSE officer, risk-assessed by a competent person, reviewed by the main contractor's HSE manager and approved by the project manager and, on most UAE projects, the client's or consultant's HSE representative. Work should not start until every required signature is in place and the crew has been briefed.

Is an MSRA a legal requirement in the UAE?

The document name is not written into UAE law, but the duty is. Federal Decree-Law No. 33 of 2021 and Ministerial Decision No. 32 of 2022 require employers to assess and control occupational risk, and ADOSH-SF, Dubai Municipality and Trakhees requirements each expect a documented method statement and risk assessment for high-risk work. The MSRA is how contractors evidence that duty.

What should an MSRA contain?

Scope and location, step-by-step method, plant and equipment, competency of the persons involved, hazards and 5×5 risk scores before and after controls, permits required, emergency and rescue arrangements, references to standards, appendices such as drawings and certificates, and the signature block.

How long is an MSRA valid?

Until the method, the site conditions, the plant or the personnel change — then it must be revised and re-approved. Many clients also require an annual review even where nothing has changed.

What is the difference between an MSRA and a permit to work?

The MSRA describes how the task will be done safely; the permit to work authorises that specific task for a defined location, crew and time window. A permit should always reference an approved, current MSRA.

Do MSRAs need to be in Arabic?

Authorities generally accept English submissions, but the workforce briefing must be given in a language the crew understands. On UAE sites that commonly means Arabic, Hindi, Urdu, Tagalog or Malayalam alongside the English document, with the briefing recorded on the register.

Next step

Turn this into evidence you can hand over

Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.

  • Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
  • Usable the same dayTemplates and registers are pre-filled with your company details.
  • Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.